Concrete Mix Ratio Table (M15, M20, M25) + Free Estimator
Quick answer: the M20 concrete mix ratio is 1 : 1.5 : 3 (cement : sand : aggregate). M15 is 1 : 2 : 4. For M25, 1 : 1 : 2 is often quoted on site, but IS 456 expects M25 and above to be a lab-tested design mix, not a nominal mix. One cubic metre of M20 needs about 8 bags of cement, 0.42 m³ of sand and 0.84 m³ of 20 mm aggregate.
⬇ Download the free concrete quantity estimator (Excel)
Concrete mix ratio table
| Grade | Mix ratio (C : S : A) | Strength (N/mm² at 28 days) | Typical use |
|---|---|---|---|
| M5 | 1 : 5 : 10 | 5 | Levelling course, mud mat |
| M7.5 | 1 : 4 : 8 | 7.5 | PCC below footings, masonry bedding |
| M10 | 1 : 3 : 6 | 10 | PCC flooring, non-structural work |
| M15 | 1 : 2 : 4 | 15 | PCC, pathways, light floors |
| M20 | 1 : 1.5 : 3 | 20 | RCC slabs, beams, columns and footings in houses |
| M25 | 1 : 1 : 2 (thumb rule only) | 25 | RCC for heavier loads. Use a design mix. |
"M" stands for mix, and the number is the characteristic compressive strength in N/mm² after 28 days of curing. IS 456:2000 allows nominal mixes (fixed ratios like the ones above) only for M20 or lower.
Material quantity per 1 m³ of concrete
Wet concrete shrinks when the voids fill, so you need about 1.54 m³ of dry material for 1 m³ of concrete. With cement at 1,440 kg/m³ and a 50 kg bag:
| Grade | Cement (kg) | Cement bags | Sand (m³) | Sand (cft) | Aggregate (m³) | Aggregate (cft) |
|---|---|---|---|---|---|---|
| M5 | 139 | 2.8 | 0.48 | 17.0 | 0.96 | 34.0 |
| M7.5 | 171 | 3.4 | 0.47 | 16.7 | 0.95 | 33.5 |
| M10 | 222 | 4.4 | 0.46 | 16.3 | 0.92 | 32.6 |
| M15 | 317 | 6.3 | 0.44 | 15.5 | 0.88 | 31.1 |
| M20 | 403 | 8.1 | 0.42 | 14.8 | 0.84 | 29.7 |
| M25* | 554 | 11.1 | 0.39 | 13.6 | 0.77 | 27.2 |
*M25 at the 1:1:2 thumb rule. A proper design mix usually uses less cement for the same strength. 1 m³ = 35.315 cft, and 1 brass = 100 cft.
How to calculate it yourself (M20 example)
- Dry volume = 1 m³ × 1.54 = 1.54 m³
- Sum of ratio = 1 + 1.5 + 3 = 5.5
- Cement = 1.54 ÷ 5.5 × 1 = 0.28 m³ × 1,440 = 403 kg = 8.06 bags
- Sand = 1.54 ÷ 5.5 × 1.5 = 0.42 m³ (14.8 cft)
- Aggregate = 1.54 ÷ 5.5 × 3 = 0.84 m³ (29.7 cft)
- Water ≈ cement × water-cement ratio = 403 × 0.5 ≈ 200 litres
Worked example: a 5 m × 4 m slab, 5 inches thick
5 inches ≈ 0.125 m. Volume = 5 × 4 × 0.125 = 2.5 m³, plus 5% wastage = 2.63 m³ of M20.
- Cement: about 21 bags
- Sand: 1.10 m³ (about 39 cft)
- 20 mm aggregate: 2.21 m³ (about 78 cft)
- Water: about 530 litres
These are exactly the sample numbers in our Excel estimator. Change the grade, size and your local prices, and it recalculates bags, cft and approximate material cost.
Quick table: M20 slab material per 100 sq ft
Most house owners and contractors think in square feet. For an M20 slab, without wastage:
| Slab thickness | Concrete (m³) | Cement bags | Sand (cft) | Aggregate (cft) |
|---|---|---|---|---|
| 4 inch | 0.94 | 7.6 | 14.0 | 28.0 |
| 5 inch | 1.18 | 9.5 | 17.5 | 35.0 |
| 6 inch | 1.42 | 11.4 | 21.0 | 42.0 |
For a 1,000 sq ft slab at 5 inches, multiply by 10: about 95 bags of cement, 175 cft of sand and 350 cft of aggregate, plus 5% for wastage.
Nominal mix vs design mix
A nominal mix uses fixed volume ratios like 1:1.5:3. It is simple and works for small jobs, but strength varies with the sand, aggregate and water used on that day. A design mix is worked out by a lab for your actual materials. It specifies cement, sand, aggregate, water and admixture by weight. A design mix gives reliable strength and often saves cement. That's why IS 456 requires it for M25 and above, and why ready-mix plants always supply design mixes.
Site tips for good concrete
- Don't add extra water to make concrete easier to work. More water means weaker concrete. A water-cement ratio of about 0.45–0.55 is typical. IS 456 caps it at 0.55 for RCC in moderate exposure.
- Measure by volume boxes (farma), not by shovels. One cement bag ≈ 0.035 m³, so a 35-litre box matches one bag.
- Cure for at least 7 days with ordinary Portland cement, and 10 days with blended cement or in hot, dry weather.
- Order 5–10% extra sand and aggregate for wastage and uneven surfaces.
- For RCC work, follow your structural engineer's mix design. This table is for estimating, not for design.
From estimate to site: tracking cement and labour
The estimate tells you to buy 21 bags. Knowing whether 21 bags reached the site, and how many labourers worked on the slab that day, is the harder part. In HajariBook you can log material received at each site with challans, see running stock, and mark labour hajari for the day. Your slab cost is then based on real numbers. See construction material management for how it works.
Frequently asked questions
What is the ratio of M20 concrete?
1 : 1.5 : 3, meaning 1 part cement, 1.5 parts sand and 3 parts 20 mm aggregate by volume.
How many cement bags are needed for 1 m³ of M20 concrete?
About 8 bags (403 kg) by the nominal mix method.
What is the mix ratio of M25 concrete?
1 : 1 : 2 is a common thumb rule. IS 456 expects M25 and above to be a design mix made with lab-tested proportions, which often needs less cement.
What is the difference between M15 and M20?
M20 has more cement (1:1.5:3 vs 1:2:4) and reaches 20 N/mm² instead of 15 N/mm². M15 is used for PCC; M20 is the minimum commonly used for RCC in houses.
How much sand and aggregate for one bag of cement in M20?
One 50 kg bag is about 1.23 cft. For 1:1.5:3, use about 1.84 cft of sand and 3.68 cft of aggregate per bag. On site, that's roughly one and a half farmas of sand and three farmas of aggregate for each bag.
What ratio is used for PCC under footings?
Usually M7.5 (1:4:8) or M10 (1:3:6), about 75–100 mm thick, to give the footing a clean, level base. Follow the ratio on your drawing.
How many cft are in 1 m³?
35.315 cft. One brass of sand or aggregate is 100 cft, about 2.83 m³.